Dept. of Trans. PROGRESS Serial No. Contract No. 12-081-08-48 04-0120S4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 59% 53% 04-SF-80-7.9/8.2 Federal Project: NONE Progress payment No. 30 Payment period ending: 03-20-12 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 956600620 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 42,314,039.15 3,738,499.75 2.a. Extra Work 37,820,146.56 2,063,390.26 b. Adjustment Comp. 15,834,835.92 -44,765.00 3. Materials on Hand 840,079.90 0.00 4. Earned Subject to Retention 96,809,101.53 5,757,125.01 5. Mobilization 8,020,613.00 0.00 6. Total Work Completed 103,989,634.63 7. Deductions -25,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 104,804,714.53 5,757,125.01 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 5,757,125.01