Dept. of Trans. PROGRESS Serial No. Contract No. 12-170-09-10 04-0120S4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 69% 60% 04-SF-80-7.9/8.2 Federal Project: NONE Progress payment No. 33 Payment period ending: 06-20-12 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 956600620 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 49,940,870.35 -2,807,560.70 2.a. Extra Work 45,389,414.27 5,657,179.96 b. Adjustment Comp. 22,177,760.75 4,255,126.60 3. Materials on Hand 2,500,648.90 -16,404.67 4. Earned Subject to Retention 120,008,694.27 7,088,341.19 5. Mobilization 8,020,613.00 0.00 6. Total Work Completed 125,528,658.37 7. Deductions -20,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 128,009,307.27 7,088,341.19 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 7,088,341.19