Dept. of Trans. PROGRESS Serial No. Contract No. 13-141-16-31 04-0120S4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 86% 84% 04-SF-80-7.9/8.2 Federal Project: NONE Progress payment No. 52 Payment period ending: 05-20-13 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 956600620 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 64,931,413.45 645,715.00 2.a. Extra Work 69,357,837.66 1,879,755.16 b. Adjustment Comp. 49,022,848.17 165,745.24 3. Materials on Hand 0.00 -800,231.32 4. Earned Subject to Retention 183,312,099.28 1,890,984.08 5. Mobilization 8,020,613.00 0.00 6. Total Work Completed 191,332,712.28 7. Deductions -40,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 191,292,712.28 1,890,984.08 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,890,984.08