Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 15-159-08-50 04-0120S4 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 04-SF-80-7.9/8.2 NONE Progress payment No. 078 Payment period ending: 06-23-14 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 956600620 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 69,867,462.90 -167,000.00 2. a. Extra Work 120,522,276.87 400,917.95 b. Adustment Comp. 58,290,699.67 6,780.96 3. Materials on Hand 4. Earned Subject to Retention 248,680,439.44 240,698.91 5. Mobilization 8,020,613.00 0.00 6. Total Work Completed 256,701,052.44 7. Deductions -31,000.00 -31,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 256,670,052.44 209,698.91 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 209,698.91