Dept. of Trans. PROGRESS Serial No. Contract No. 15-168-11-06 04-0120T4 PROGRESS PAYMENT VOUCHER %complete: %time: 71% 54% Location: Federal Project: 04-SF-80-12.6/13.9 NONE Progress payment No. 032 Payment period ending: 06-20-15 CALIFORNIA ENGINEERING CONTRACTORS INC/SILVERADO CONTRACTORS INC VENTURE 20 HAPPY VALLEY ROAD PLEASANTON CA 94566 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 49,877,068.08 2,149,643.50 2. a. Extra Work 32,700,928.17 796,771.01 b. Adustment Comp. 7,664,920.85 1,821.61 3. Materials on Hand 331,664.25 -83,191.90 4. Earned Subject to Retention 90,574,581.35 2,865,044.22 5. Mobilization 8,600,000.00 0.00 6. Total Work Completed 98,842,917.10 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 99,174,581.35 2,865,044.22 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,865,044.22