Dept. of Trans. PROGRESS Serial No. Contract No. 16-356-08-27 04-0120T4 PROGRESS PAYMENT VOUCHER %complete: %time: 92% 87% Location: Federal Project: 04-SF-80-12.6/13.9 NONE Progress payment No. 055 Payment period ending: 12-21-16 CALIF ENG CONTRACTORS INC/SILVERADO CONTRACTORS INC JNT VENT 20 HAPPY VALLEY RD PLEASANTON CA 94566 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 73,531,027.18 1,185,950.00 2. a. Extra Work 47,921,917.23 861,721.18 b. Adustment Comp. 18,464,016.67 1,330,398.73 3. Materials on Hand 193,682.16 -102,952.28 4. Earned Subject to Retention 140,110,643.24 3,275,117.63 5. Mobilization 8,600,000.00 0.00 6. Total Work Completed 148,516,961.08 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 148,710,643.24 3,275,117.63 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,275,117.63