Dept. of Trans. PROGRESS Serial No. Contract No. 17-053-07-18 04-0120T4 PROGRESS PAYMENT VOUCHER %complete: %time: 94% 93% Location: Federal Project: 04-SF-80-12.6/13.9 NONE Progress payment No. 057 Payment period ending: 02-22-17 CALIF ENG CONTRACTORS INC/SILVERADO CONTRACTORS INC JNT VENT 20 HAPPY VALLEY RD PLEASANTON CA 94566 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 74,211,691.11 -22,643.50 2. a. Extra Work 49,208,066.80 442,808.24 b. Adustment Comp. 21,717,357.10 2,053,460.38 3. Materials on Hand 151,518.26 -42,163.90 4. Earned Subject to Retention 145,288,633.27 2,431,461.22 5. Mobilization 8,600,000.00 0.00 6. Total Work Completed 153,737,115.01 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 153,888,633.27 2,431,461.22 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,431,461.22