Dept. of Trans. PROGRESS Serial No. Contract No. 17-170-14-19 04-0120T4 PROGRESS PAYMENT VOUCHER %complete: %time: 92% 100% Location: Federal Project: 04-SF-80-12.6/13.9 NONE Progress payment No. 061 Payment period ending: 06-19-17 CALIF ENG CONTRACTORS INC/SILVERADO CONTRACTORS INC JNT VENT 20 HAPPY VALLEY RD PLEASANTON CA 94566 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 74,015,791.01 -110,465.00 2. a. Extra Work 52,865,816.84 1,135,391.87 b. Adustment Comp. 25,346,401.42 805,812.02 3. Materials on Hand 108,158.53 -12,218.64 4. Earned Subject to Retention 152,336,167.80 1,818,520.25 5. Mobilization 8,600,000.00 0.00 6. Total Work Completed 160,828,009.27 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 160,936,167.80 1,818,520.25 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,818,520.25