Dept. of Trans. PROGRESS Serial No. Contract No. 00-202-14-45 04-013014 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 17% 14% 04-CC-80-13.8/14.7 Federal Project: 04-SOL-80-0.0/0.5 NONE Progress payment No. 06 Payment period ending: 07-20-00 FCI CONSTRUCTORS INC CLEVELAND BRIDGE CALIFORNIA INC A JOINT VENTURE 90 GREAT OAKS BLVD SUITE 105 SAN JOSE CA 95119 Escrow No. 01451 Total Estimate This Estimate 1. Contract Itms Without Mobil. 18,689,485.82 6,741,556.45 2.a. Extra Work 2,642.76 0.00 b. Adjustment Comp. 3. Materials on Hand 5,126,051.28 75,946.70 4. Earned Subject to Retention 23,818,179.86 6,817,503.15 5. Mobilization 13,500,000.00 4,500,000.00 6. Total Work Completed 32,192,128.58 7. Deductions -400.00 -400.00 8. a.Contract Retentions -2,381,817.99 -681,750.32 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 34,935,961.87 10,635,352.83 10. Reduction Amt to Escrow 11. Payment to Escrow 2,381,810.00 12. Net Pymt. this Estimate 10,635,352.83