Dept. of Trans. PROGRESS Serial No. Contract No. 01-201-18-02 04-013014 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 50% 34% 04-CC-80-13.8/14.7 Federal Project: 04-SOL-80-0.0/0.5 NONE Progress payment No. 18 Payment period ending: 07-20-01 FCI CONSTRUCTORS INC CLEVELAND BRIDGE CALIFORNIA INC A JOINT VENTURE 90 GREAT OAKS BLVD SUITE 105 SAN JOSE CA 95119 Escrow No. 01451 Total Estimate This Estimate 1. Contract Itms Without Mobil. 75,246,356.01 6,557,593.28 2.a. Extra Work 2,909,990.48 -8,932.31 b. Adjustment Comp. 10,427,773.87 2,304,355.82 3. Materials on Hand 6,727,076.42 -433,368.14 4. Earned Subject to Retention 95,311,196.78 8,419,648.65 5. Mobilization 18,000,000.00 900,000.00 6. Total Work Completed 106,584,120.36 7. Deductions -10,369.70 -394.70 8. a.Contract Retentions -4,765,559.84 -420,982.43 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 108,535,267.24 8,898,271.52 10. Reduction Amt to Escrow 11. Payment to Escrow 4,765,550.00 12. Net Pymt. this Estimate 8,898,271.52