Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 03-029-13-20 04-013014 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 80% 69% 04-CC-80-13.8/14.7 Federal Project: 04-SOL-80-0.0/0.5 NONE Progress payment No. 37 Payment period ending: 01-28-03 FCI CONSTRUCTORS INC CLEVELAND BRIDGE CALIFORNIA INC A JOINT VENTURE 2100 GOODYEAR ROAD BENICIA, CA 94510 Escrow No. 01451 Total Estimate This Estimate 1. Contract Itms Without Mobil. 136,251,305.87 0.00 2.a. Extra Work 4,953,260.94 157,476.77 b. Adjustment Comp. 16,048,710.56 1,246,632.00 3. Materials on Hand 976,731.97 0.00 4. Earned Subject to Retention 158,230,009.34 1,404,108.77 5. Mobilization 18,000,000.00 0.00 6. Total Work Completed 175,253,277.37 7. Deductions -11,059.65 20,000.00 8. a.Contract Retentions -7,911,500.47 -70,205.44 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 168,307,449.22 1,353,903.33 10. Reduction Amt to Escrow 11. Payment to Escrow 7,911,500.00 12. Net Pymt. this Estimate 1,353,903.33