Dept. of Trans. PROGRESS Serial No. Contract No. 01-081-15-38 04-013084 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 11% 21% 04-SOL-680-1.5/ .0 Federal Project: NONE Progress payment No. 04 Payment period ending: 03-20-01 DIABLO CONTRACTORS INC 760 SAN RAMON VALLEY BLVD 103 DANVILLE CA 94526 Escrow No. 01667 Total Estimate This Estimate 1. Contract Itms Without Mobil. 424,870.00 199,180.00 2.a. Extra Work 12,953.86 8,584.22 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 437,823.86 207,764.22 5. Mobilization 350,000.00 350,000.00 6. Total Work Completed 787,823.86 7. Deductions 8. a.Contract Retentions -43,782.39 -20,776.43 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 744,041.47 536,987.79 10. Reduction Amt to Escrow 11. Payment to Escrow 43,780.00 12. Net Pymt. this Estimate 536,987.79