Dept. of Trans. PROGRESS Serial No. Contract No. 06-167-07-25 04-013094 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 64% 45% 04-CC-80-13.7/14.1 Federal Project: 04-SOL-80-0.0/0.3 NONE Progress payment No. 14 Payment period ending: 06-20-06 CALIFORNIA ENGINEERING CONTRACTORS INC 20 HAPPY VALLEY ROAD PLEASANTON CA 94566 Escrow No. 02196 Total Estimate This Estimate 1. Contract Itms Without Mobil. 15,558,682.94 328,130.00 2.a. Extra Work 753,181.48 13,632.00 b. Adjustment Comp. 136,040.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 16,447,904.42 341,762.00 5. Mobilization 2,880,000.00 0.00 6. Total Work Completed 19,327,904.42 7. Deductions -6,000.00 -6,000.00 8. a.Contract Retentions -822,395.22 -17,088.10 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 18,499,509.20 318,673.90 10. Reduction Amt to Escrow 11. Payment to Escrow 822,390.00 12. Net Pymt. this Estimate 318,673.90