Dept. of Trans. PROGRESS Serial No. Contract No. 06-230-07-15 04-013094 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 67% 48% 04-CC-80-13.7/14.1 Federal Project: 04-SOL-80-0.0/0.3 NONE Progress payment No. 16 Payment period ending: 08-20-06 CALIFORNIA ENGINEERING CONTRACTORS INC 20 HAPPY VALLEY ROAD PLEASANTON CA 94566 Escrow No. 02196 Total Estimate This Estimate 1. Contract Itms Without Mobil. 16,280,990.94 411,503.00 2.a. Extra Work 770,314.90 15,167.07 b. Adjustment Comp. 483,817.00 347,777.00 3. Materials on Hand 4. Earned Subject to Retention 17,535,122.84 774,447.07 5. Mobilization 2,880,000.00 0.00 6. Total Work Completed 20,415,122.84 7. Deductions -2,800.00 1,600.00 8. a.Contract Retentions -876,756.14 -38,722.35 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 19,535,566.70 737,324.72 10. Reduction Amt to Escrow 11. Payment to Escrow 876,750.00 12. Net Pymt. this Estimate 737,324.72