Dept. of Trans. PROGRESS Serial No. Contract No. 07-358-13-55 04-0130E4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 80% 95% 04-CC-80-12.6/13.8 Federal Project: NONE Progress payment No. 05 Payment period ending: 12-20-07 O C JONES AND SONS INC 1520 FOURTH STREET BERKELEY CA 94710 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 359,442.50 30,710.00 2.a. Extra Work 4,795.35 3,229.80 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 364,237.85 33,939.80 5. Mobilization 46,000.00 0.00 6. Total Work Completed 410,237.85 7. Deductions 8. a.Contract Retentions -18,211.89 -1,696.99 b. Unsatisfactory Prog. -1,696.99 -1,696.99 c. Reduction after 95% Comp. 9. Total pay to Contractor 390,328.97 30,545.82 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 30,545.82