Dept. of Trans. PROGRESS Serial No. Contract No. 08-165-07-43 04-0130K4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 3% 13% 04-CC-80-13.6/ .0 Federal Project: 04-SOL-80-0.5/ .0 NONE Progress payment No. 01 Payment period ending: 06-20-08 P AND D LANDSCAPE MANAGEMENT SERVICES 999 TOWN AND COUNTRY RD 4TH F ORANGE CA 92868 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 8,888.35 8,888.35 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 8,888.35 8,888.35 5. Mobilization 6. Total Work Completed 8,888.35 7. Deductions 8. a.Contract Retentions -888.84 -888.84 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 7,999.51 7,999.51 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 7,999.51