Dept. of Trans. PROGRESS Serial No. Contract No. 09-141-08-00 04-0130K4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 04-CC-80-13.6/ .0 Federal Project: 04-SOL-80-0.5/ .0 NONE Progress payment No. 12 Payment period ending: 05-20-09 P AND D LANDSCAPE MANAGEMENT SERVICES 999 TOWN AND COUNTRY RD 4TH F ORANGE CA 92868 Escrow No. 02374 Total Estimate This Estimate 1. Contract Itms Without Mobil. 206,373.79 3,486.45 2.a. Extra Work 6,078.62 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 212,452.41 3,486.45 5. Mobilization 33,407.00 0.00 6. Total Work Completed 245,859.41 7. Deductions 8. a.Contract Retentions -10,622.62 -174.32 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 235,236.79 3,312.13 10. Reduction Amt to Escrow 11. Payment to Escrow 10,440.00 12. Net Pymt. this Estimate 3,312.13