Dept. of Trans. PROGRESS Serial No. Contract No. 16-231-12-58 04-013524 PROGRESS PAYMENT VOUCHER %complete: %time: 69% 43% Location: Federal Project: 04-SF-80-8.6/8.9 NONE 04-ALA-80-0.0/1.2 Progress payment No. 015 Payment period ending: 08-20-16 CALIF ENG CONTRACTORS INC/SILVERADO CONTRACTORS INC JNT VENT 20 HAPPY VALLEY RD PLEASANTON CA 94566 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 41,262,677.57 2,561,528.05 2. a. Extra Work 2,655,211.26 230,653.38 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 43,917,888.83 2,792,181.43 5. Mobilization 6,800,000.00 0.00 6. Total Work Completed 50,717,888.83 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 50,717,888.83 2,792,181.43 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,792,181.43