Dept. of Trans. PROGRESS Serial No. Contract No. 18-232-14-22 04-013584 PROGRESS PAYMENT VOUCHER %complete: %time: 53% 52% Location: Federal Project: 04-SF-80-8.3 NONE 04-ALA-80-0.8/1.2 Progress payment No. 005 Payment period ending: 08-20-18 KIEWIT/MANSON A JV 4650 BUSINESS CENTER DR FAIRFIELD CA 94534 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 21,702,445.92 6,021,445.68 2. a. Extra Work 237,060.93 135,987.44 b. Adustment Comp. 504,784.00 504,784.00 3. Materials on Hand 124,870.00 124,870.00 4. Earned Subject to Retention 22,569,160.85 6,787,087.12 5. Mobilization 1,788,100.00 89,405.00 6. Total Work Completed 24,232,390.85 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 24,357,260.85 6,876,492.12 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 6,876,492.12