Dept. of Trans. PROGRESS Serial No. Contract No. 19-051-08-46 04-013584 PROGRESS PAYMENT VOUCHER %complete: %time: 86% 64% Location: Federal Project: 04-SF-80-8.3 NONE 04-ALA-80-0.8/1.2 Progress payment No. 011 Payment period ending: 02-20-19 KIEWIT/MANSON A JV 4650 BUSINESS CENTER DR FAIRFIELD CA 94534 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 41,194,621.52 759,748.00 2. a. Extra Work 1,764,914.77 926,833.30 b. Adustment Comp. 2,002,359.96 11,463.96 3. Materials on Hand 4. Earned Subject to Retention 44,961,896.25 1,698,045.26 5. Mobilization 1,788,100.00 0.00 6. Total Work Completed 46,749,996.25 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 46,749,996.25 1,698,045.26 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,698,045.26