Dept. of Trans. PROGRESS Serial No. Contract No. 14-205-10-33 04-014084 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 73% 56% 04-ALA-80-2.5/ .0 Federal Project: NONE Progress payment No. 16 Payment period ending: 07-20-14 F & H CONSTRUCTION P O BOX 2329 LODI CA 95241 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 23,808,477.30 1,719,161.50 2.a. Extra Work 311,227.44 148,062.94 b. Adjustment Comp. 301,476.92 133,346.50 3. Materials on Hand 4. Earned Subject to Retention 24,421,181.66 2,000,570.94 5. Mobilization 6. Total Work Completed 24,421,181.66 7. Deductions -10,000.00 -10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 24,411,181.66 1,990,570.94 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,990,570.94