Dept. of Trans. PROGRESS Serial No. Contract No. 15-111-08-30 04-014084 PROGRESS PAYMENT VOUCHER %complete: %time: 96% 83% Location: Federal Project: 04-ALA-80-2.5 NONE Progress payment No. 025 Payment period ending: 04-20-15 F & H CONSTRUCTION P O BOX 2329 LODI CA 95241 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 31,237,132.19 153,077.55 2. a. Extra Work 1,375,737.54 101,929.03 b. Adustment Comp. 778,575.62 -2,399.00 3. Materials on Hand 4. Earned Subject to Retention 33,391,445.35 252,607.58 5. Mobilization 6. Total Work Completed 33,391,445.35 7. Deductions -30,000.00 25,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 33,361,445.35 277,607.58 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 277,607.58