Dept. of Trans. PROGRESS Serial No. Contract No. 15-174-11-46 04-014084 PROGRESS PAYMENT VOUCHER %complete: %time: 97% 84% Location: Federal Project: 04-ALA-80-2.5 NONE Progress payment No. 027 Payment period ending: 06-20-15 F & H CONSTRUCTION P O BOX 2329 LODI CA 95241 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 31,401,250.19 163,348.00 2. a. Extra Work 1,455,267.59 25,149.32 b. Adustment Comp. 746,377.62 -32,198.00 3. Materials on Hand 4. Earned Subject to Retention 33,602,895.40 156,299.32 5. Mobilization 6. Total Work Completed 33,602,895.40 7. Deductions -30,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 33,572,895.40 156,299.32 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 156,299.32