Dept. of Trans. SEMI-FINAL Serial No. Contract No. 16-132-08-51 04-014084 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 04-ALA-80-2.5 NONE Progress payment No. 032 Payment period ending: 09-25-15 F & H CONSTRUCTION PO BOX 2329 LODI CA 95241 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 32,531,552.43 61,145.82 2. a. Extra Work 1,762,564.81 42,167.46 b. Adustment Comp. 976,040.85 0.00 3. Materials on Hand 4. Earned Subject to Retention 35,270,158.09 103,313.28 5. Mobilization 6. Total Work Completed 35,270,158.09 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 35,270,158.09 103,313.28 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 103,313.28