Dept. of Trans. PROGRESS Serial No. Contract No. 16-049-14-18 04-014104 PROGRESS PAYMENT VOUCHER %complete: %time: 69% 37% Location: Federal Project: 04-ALA-80-1.8 NONE Progress payment No. 014 Payment period ending: 02-20-16 TABER CONSTRUCTION INC PO BOX 1309 MARTINEZ CA 94553 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,733,475.05 1,500,900.00 2. a. Extra Work 248,305.55 22,507.32 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 9,981,780.60 1,523,407.32 5. Mobilization 6. Total Work Completed 9,981,780.60 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 9,981,780.60 1,523,407.32 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,523,407.32