Dept. of Trans. PROGRESS Serial No. Contract No. 19-112-14-27 04-014114 PROGRESS PAYMENT VOUCHER %complete: %time: 59% 60% Location: Federal Project: 04-ALA-80-1.8 NONE Progress payment No. 011 Payment period ending: 04-20-19 THOMPSON BUILDERS CORPORATION 250 BEL MARIN KEYS BLVD BLDG NOVATO CA 94949 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,946,718.75 838,611.00 2. a. Extra Work 360,621.19 18,910.47 b. Adustment Comp. -27,947.64 0.00 3. Materials on Hand 4. Earned Subject to Retention 10,279,392.30 857,521.47 5. Mobilization 6. Total Work Completed 10,279,392.30 7. Deductions -5,122.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 10,274,270.30 857,521.47 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 857,521.47