Dept. of Trans. PROGRESS Serial No. Contract No. 06-080-09-37 04-015124 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 91% 73% 04-SM-84-R27.7/R28.2 Federal Project: NONE Progress payment No. 31 Payment period ending: 03-20-06 AMLAND 3168 KNIGHTS BRIDGE RD SAN JOSE CA 95132 Escrow No. 02123 Total Estimate This Estimate 1. Contract Itms Without Mobil. 357,155.00 2,430.00 2.a. Extra Work 3,310.00 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 360,465.00 2,430.00 5. Mobilization 35,000.00 0.00 6. Total Work Completed 395,465.00 7. Deductions 8. a.Contract Retentions -18,023.25 -121.50 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 377,441.75 2,308.50 10. Reduction Amt to Escrow 11. Payment to Escrow 17,900.00 12. Net Pymt. this Estimate 2,308.50