Dept. of Trans. PROGRESS Serial No. Contract No. 08-052-09-04 04-016014 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 11% 5% 04-ALA-92-4.8/6.7 Federal Project: 04-ALA-880-15.6/17.6 NONE Progress payment No. 04 Payment period ending: 02-20-08 F C I CONSTRUCTORS GRANITE A JOINT VENTURE OF F C I CONSTRUCTORS INC AND GRANITE CONSTRUCTION COMPANY 2100 GOODYEAR RD BENICIA CA 94510Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 8,643,185.94 1,649,998.49 2.a. Extra Work 146,052.46 108,506.75 b. Adjustment Comp. 300,000.00 0.00 3. Materials on Hand 546,890.43 -27,491.32 4. Earned Subject to Retention 9,636,128.83 1,731,013.92 5. Mobilization 6,000,000.00 0.00 6. Total Work Completed 15,089,238.40 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 15,636,128.83 1,731,013.92 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,731,013.92