Dept. of Trans. PROGRESS Serial No. Contract No. 11-024-08-26 04-040804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 66% 51% 04-SF-80-6.7/7.8 Federal Project: NONE Progress payment No. 02 Payment period ending: 01-20-11 BENTANCOURT BROS CONSTRUCTION INC 5933 NORTHFRONT ROAD LIVERMORE CA 94551 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 200,063.50 108,823.50 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 200,063.50 108,823.50 5. Mobilization 122,550.00 25,800.00 6. Total Work Completed 322,613.50 7. Deductions -76,104.50 -16,022.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 246,509.00 118,601.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 118,601.50