Dept. of Trans. PROGRESS Serial No. Contract No. 09-232-14-32 04-042254 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 57% 83% 04-SM-84-R29.1/R30.2 Federal Project: 04-ALA-84-R0.0/R1.0 NONE Progress payment No. 04 Payment period ending: 08-20-09 BUGLER CONSTRUCTION 5524-C SPRINGDALE AVE., #96 PLEASANTON CA 94588 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,178,065.00 409,685.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 1,178,065.00 409,685.00 5. Mobilization 285,000.00 0.00 6. Total Work Completed 1,463,065.00 7. Deductions -32,730.35 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,430,334.65 409,685.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 409,685.00