Dept. of Trans. PROGRESS Serial No. Contract No. 12-170-11-33 04-0435E4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 84% 76% 04-SF-80-4.9/5.9 Federal Project: NONE Progress payment No. 17 Payment period ending: 06-20-12 GORDON N BALL INC 333 CAMILLE AVENUE ALAMO CA 94507 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,241,310.15 54,300.00 2.a. Extra Work 490,871.61 33,082.20 b. Adjustment Comp. 3. Materials on Hand 26,075.00 0.00 4. Earned Subject to Retention 2,758,256.76 87,382.20 5. Mobilization 260,000.00 0.00 6. Total Work Completed 2,992,181.76 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 3,018,256.76 87,382.20 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 87,382.20