Dept. of Trans. PROGRESS Serial No. Contract No. 03-170-16-17 04-0438U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 54% 68% 04-CC-580-6.1/7.8 Federal Project: 04-MRN-580-0.0/2.6 ACIM-580-2(41) Progress payment No. 38 Payment period ending: 06-20-03 TUTOR SALIBA KOCH TIDEWATER JV 15901 OLDEN STREET SYLMAR CA 91342 Escrow No. 01586 Total Estimate This Estimate 1. Contract Itms Without Mobil. 212,780,353.14 9,589,549.88 2.a. Extra Work 20,890,840.48 930,489.07 b. Adjustment Comp. 13,392,887.80 678,669.21 3. Materials on Hand 45,203,491.00 874,939.00 4. Earned Subject to Retention 292,267,572.42 12,073,647.16 5. Mobilization 44,487,318.00 0.00 6. Total Work Completed 291,551,399.42 7. Deductions -101,769.41 -9,110.87 8. a.Contract Retentions -14,613,378.62 -603,682.36 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 322,039,742.39 11,460,853.93 10. Reduction Amt to Escrow 11. Payment to Escrow 9,977,670.00 12. Net Pymt. this Estimate 11,460,853.93