Dept. of Trans. PROGRESS Serial No. Contract No. 05-167-15-49 04-049044 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 11% 28% 04-SF-80-6.0/7.5 Federal Project: NONE Progress payment No. 03 Payment period ending: 06-20-05 CALIFORNIA ENGINEERING CONTRACTORS INC 20 HAPPY VALLEY ROAD PLEASANTON CA 94566 Escrow No. 02195 Total Estimate This Estimate 1. Contract Itms Without Mobil. 215,325.00 70,470.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 371,895.77 0.00 4. Earned Subject to Retention 587,220.77 70,470.00 5. Mobilization 455,250.00 151,750.00 6. Total Work Completed 670,575.00 7. Deductions 8. a.Contract Retentions -58,722.08 -7,047.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 983,748.69 215,173.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 215,173.00