Dept. of Trans. PROGRESS Serial No. Contract No. 06-020-07-31 04-049044 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 61% 85% 04-SF-80-6.0/7.5 Federal Project: NONE Progress payment No. 10 Payment period ending: 01-20-06 CALIFORNIA ENGINEERING CONTRACTORS INC 20 HAPPY VALLEY ROAD PLEASANTON CA 94566 Escrow No. 02195 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,111,798.44 894,328.35 2.a. Extra Work 210,972.00 210,972.00 b. Adjustment Comp. 3. Materials on Hand 1,409,230.00 -111,828.00 4. Earned Subject to Retention 4,732,000.44 993,472.35 5. Mobilization 607,000.00 0.00 6. Total Work Completed 3,929,770.44 7. Deductions 8. a.Contract Retentions -236,600.02 -49,673.62 b. Unsatisfactory Prog. -176,770.13 -49,673.62 c. Reduction after 95% Comp. 9. Total pay to Contractor 4,925,630.29 894,125.11 10. Reduction Amt to Escrow 11. Payment to Escrow 236,600.00 12. Net Pymt. this Estimate 894,125.11