Dept. of Trans. PROGRESS Serial No. Contract No. 13-057-09-04 04-049074 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 99% 94% 04-CC-80-13.9/14.2 Federal Project: 04-SOL-80-0.0/0.2 NONE Progress payment No. 10 Payment period ending: 02-20-13 GOLDEN STATE BRIDGE INC 2990 BAY VISTA COURT, SUITE D BENICIA, CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 15,207,269.50 1,568,293.50 2.a. Extra Work 362,547.95 256,511.60 b. Adjustment Comp. 94,813.97 44.31 3. Materials on Hand 0.00 -771,657.24 4. Earned Subject to Retention 15,664,631.42 1,053,192.17 5. Mobilization 1,600,000.00 0.00 6. Total Work Completed 17,264,631.42 7. Deductions -990.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 17,263,641.42 1,053,192.17 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,053,192.17