Dept. of Trans. PROGRESS Serial No. Contract No. 04-264-15-55 04-0A0504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 33% 52% 04-NAP-29-4.4/5.2 Federal Project: ACST-P029(95) P-P029(95) Progress payment No. 02 Payment period ending: 09-20-04 O C JONES AND SONS INC 1520 FOURTH STREET BERKELEY CA 94710 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 497,323.45 433,669.96 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 497,323.45 433,669.96 5. Mobilization 199,500.00 199,500.00 6. Total Work Completed 696,823.45 7. Deductions -691.41 -691.41 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 696,132.04 632,478.55 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 632,478.55