Dept. of Trans. PROGRESS Serial No. Contract No. 07-111-07-22 04-0A1304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 19% 33% 04-SCL-85-R22.0/R23.6 Federal Project: 04-SCL-237-R0.0/R1.1 NONE Progress payment No. 05 Payment period ending: 04-20-07 WATKIN AND BORTOLUSSI INC FORSTER AND KROEGER LANDSCAPE MAINTENANCE INC A JOINT VENTURE 77 LARKSPUR STREET SAN RAFAEL CA 949014886Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 379,564.50 260,239.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 157,619.94 -8,812.02 4. Earned Subject to Retention 537,184.44 251,426.98 5. Mobilization 252,000.00 84,000.00 6. Total Work Completed 631,564.50 7. Deductions 8. a.Contract Retentions -53,718.44 -25,142.69 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 735,466.00 310,284.29 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 310,284.29