Dept. of Trans. PROGRESS Serial No. Contract No. 11-202-08-04 04-0A1844 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 8% 3% 04-SON-101-7.1/8.9 Federal Project: NONE Progress payment No. 02 Payment period ending: 07-20-11 GHILOTTI CONSTRUCTION COMPANY INC 246 GHILOTTI AVE SANTA ROSA CA 95407 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 466,221.20 363,119.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 76,509.35 0.00 4. Earned Subject to Retention 542,730.55 363,119.00 5. Mobilization 444,500.00 444,500.00 6. Total Work Completed 910,721.20 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 987,230.55 807,619.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 807,619.00