Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 11-033-09-35 04-0A18U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 45% 41% 04-SON-101-8.9/13.9 Federal Project: NONE Progress payment No. 14 Payment period ending: 01-20-11 GHILOTTI CONSTRUCTION COMPANY INC. 246 GHILOTTI AVE SANTA ROSA CA 95407 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 19,487,159.26 78,350.00 2.a. Extra Work 721,170.27 3,367.30 b. Adjustment Comp. 206,052.38 0.00 3. Materials on Hand 389,308.70 0.00 4. Earned Subject to Retention 20,803,690.61 81,717.30 5. Mobilization 2,132,906.75 0.00 6. Total Work Completed 22,547,288.66 7. Deductions -5,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 22,931,597.36 81,717.30 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 81,717.30