Dept. of Trans. PROGRESS Serial No. Contract No. 06-020-07-31 04-0A2604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 23% 25% 04-SM-280-M27.4/ .0 Federal Project: 04-SF-280-R0.0/ .0 NONE Progress payment No. 01 Payment period ending: 01-20-06 BUGLER CONSTRUCTION 47000 WARM SPRINGS BLVD 101 FREMONT CA 94539 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 78,200.00 78,200.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 78,200.00 78,200.00 5. Mobilization 30,000.00 30,000.00 6. Total Work Completed 108,200.00 7. Deductions 8. a.Contract Retentions -7,820.00 -7,820.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 100,380.00 100,380.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 100,380.00