Dept. of Trans. PROGRESS Serial No. Contract No. 12-296-09-18 04-0A5354 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 49% 26% 04-SOL-80-14.3/14.4 Federal Project: ACNH-X095(23) Progress payment No. 06 Payment period ending: 10-20-12 O C JONES & SONS INC 1520 FOURTH STREET BERKELEY CA 94710 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 18,507,475.45 5,875,817.29 2.a. Extra Work 131,872.73 82,336.65 b. Adjustment Comp. 13,766.93 7,618.92 3. Materials on Hand 180,643.55 -115,600.19 4. Earned Subject to Retention 18,833,758.66 5,850,172.67 5. Mobilization 3,325,000.00 0.00 6. Total Work Completed 21,978,115.11 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 22,158,758.66 5,850,172.67 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 5,850,172.67