Dept. of Trans. PROGRESS Serial No. Contract No. 22-110-14-26 04-0A5394 PROGRESS PAYMENT VOUCHER %complete: %time: 80% 66% Location: Federal Project: 04-SOL-80-12.0/13.1 NONE Progress payment No. 019 Payment period ending: 04-20-22 KIEWIT INFRASTRUCTURE WEST CO. 4650 BUSINESS CENTER DR FAIRFIELD CA 94534 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 44,185,346.38 2,263,608.11 2. a. Extra Work 1,670,014.48 70,058.89 b. Adustment Comp. 466,074.79 0.00 3. Materials on Hand 219,195.05 -3,768.28 4. Earned Subject to Retention 46,540,630.70 2,329,898.72 5. Mobilization 4,547,720.21 0.00 6. Total Work Completed 50,869,155.86 7. Deductions -14,369.50 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 51,073,981.41 2,329,898.72 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,329,898.72