Dept. of Trans. PROGRESS Serial No. Contract No. 26-140-10-00 04-0A53T4 PROGRESS PAYMENT VOUCHER %complete: %time: 36% 20% Location: Federal Project: 04-SOL-12-L1.8/L3.2 NONE 04-SOL-80-13.4/17.2 Progress payment No. 010 Payment period ending: 05-20-26 KIEWIT INFRASTRUCTURE WEST CO. 4650 BUSINESS CENTER DR FAIRFIELD CA 94534 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 46,631,125.26 4,968,140.51 2. a. Extra Work 643,626.32 60,485.99 b. Adustment Comp. 418,650.00 216,916.00 3. Materials on Hand 153,148.52 0.00 4. Earned Subject to Retention 47,846,550.10 5,245,542.50 5. Mobilization 7,372,971.54 0.00 6. Total Work Completed 55,066,373.12 7. Deductions -7,420.50 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 55,212,101.14 5,245,542.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 5,245,542.50