Dept. of Trans. PROGRESS Serial No. Contract No. 26-201-15-15 04-0A53T4 PROGRESS PAYMENT VOUCHER %complete: %time: 43% 25% Location: Federal Project: 04-SOL-12-L1.8/L3.2 NONE 04-SOL-80-13.4/17.2 Progress payment No. 012 Payment period ending: 07-20-26 KIEWIT INFRASTRUCTURE WEST CO. 4650 BUSINESS CENTER DR FAIRFIELD CA 94534 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 57,463,600.20 5,647,794.18 2. a. Extra Work 837,232.15 143,448.05 b. Adustment Comp. 454,680.49 36,030.49 3. Materials on Hand 153,148.52 0.00 4. Earned Subject to Retention 58,908,661.36 5,827,272.72 5. Mobilization 7,372,971.54 0.00 6. Total Work Completed 66,128,484.38 7. Deductions -7,420.50 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 66,274,212.40 5,827,272.72 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 5,827,272.72