Dept. of Trans. PROGRESS Serial No. Contract No. 07-233-07-24 04-0A6204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 6% 8% 04-SON-12-34.0/34.3 Federal Project: NONE Progress payment No. 04 Payment period ending: 08-20-07 NORTH BAY CONSTRUCTION INC P O BOX 6004 PETALUMA CA 949556004 Escrow No. 02288 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,750.00 0.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 14,821.51 14,821.51 4. Earned Subject to Retention 20,571.51 14,821.51 5. Mobilization 20,500.00 20,500.00 6. Total Work Completed 26,250.00 7. Deductions 8. a.Contract Retentions -2,057.15 -1,482.15 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 39,014.36 33,839.36 10. Reduction Amt to Escrow 11. Payment to Escrow 2,050.00 12. Net Pymt. this Estimate 33,839.36