Dept. of Trans. PROGRESS Serial No. Contract No. 07-324-08-15 04-0A6204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 29% 8% 04-SON-12-34.0/34.3 Federal Project: NONE Progress payment No. 05 Payment period ending: 11-20-07 NORTH BAY CONSTRUCTION INC P O BOX 6004 PETALUMA CA 949556004 Escrow No. 02288 Total Estimate This Estimate 1. Contract Itms Without Mobil. 86,077.00 80,327.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 0.00 -14,821.51 4. Earned Subject to Retention 86,077.00 65,505.49 5. Mobilization 38,950.00 18,450.00 6. Total Work Completed 125,027.00 7. Deductions 8. a.Contract Retentions -7,769.46 -5,712.31 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 117,257.54 78,243.18 10. Reduction Amt to Escrow 11. Payment to Escrow 7,760.00 12. Net Pymt. this Estimate 78,243.18