Dept. of Trans. PROGRESS Serial No. Contract No. 08-052-07-32 04-0A6204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 85% 50% 04-SON-12-34.0/34.3 Federal Project: NONE Progress payment No. 08 Payment period ending: 02-20-08 NORTH BAY CONSTRUCTION INC P O BOX 6004 PETALUMA CA 949556004 Escrow No. 02288 Total Estimate This Estimate 1. Contract Itms Without Mobil. 298,139.60 28,542.86 2.a. Extra Work 6,488.34 3,568.48 b. Adjustment Comp. 52,550.00 52,550.00 3. Materials on Hand 4. Earned Subject to Retention 357,177.94 84,661.34 5. Mobilization 41,000.00 0.00 6. Total Work Completed 398,177.94 7. Deductions 8. a.Contract Retentions -17,858.90 -4,233.07 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 380,319.04 80,428.27 10. Reduction Amt to Escrow 11. Payment to Escrow 17,850.00 12. Net Pymt. this Estimate 80,428.27