Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 08-154-13-42 04-0A6204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 04-SON-12-34.0/34.3 Federal Project: NONE Progress payment No. 11 Payment period ending: 05-06-08 NORTH BAY CONSTRUCTION INC P O BOX 6004 PETALUMA CA 949556004 Escrow No. 02288 Total Estimate This Estimate 1. Contract Itms Without Mobil. 367,406.23 0.00 2.a. Extra Work 7,889.85 0.00 b. Adjustment Comp. 55,322.10 0.00 3. Materials on Hand 4. Earned Subject to Retention 430,618.18 0.00 5. Mobilization 41,000.00 0.00 6. Total Work Completed 471,618.18 7. Deductions 8. a.Contract Retentions -21,530.91 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 21,530.91 21,530.91 9. Total pay to Contractor 471,618.18 21,530.91 10. Reduction Amt to Escrow -21,530.00 -21,530.00 11. Payment to Escrow 21,530.00 12. Net Pymt. this Estimate 0.91