Dept. of Trans. PROGRESS Serial No. Contract No. 17-115-15-15 04-0A7104 PROGRESS PAYMENT VOUCHER %complete: %time: 53% 49% Location: Federal Project: 04-ALA-880-28.4/29.2 NHPA-8801(70) Progress payment No. 034 Payment period ending: 04-20-17 RGW CONSTRUCTION INC 550 GREENVILLE RD LIVERMORE CA 94550 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 21,820,802.67 620,081.60 2. a. Extra Work 3,764,261.77 1,975.17 b. Adustment Comp. 245,213.02 65,000.00 3. Materials on Hand 634,367.30 -47,982.15 4. Earned Subject to Retention 26,464,644.76 639,074.62 5. Mobilization 5,080,000.00 254,000.00 6. Total Work Completed 30,910,277.46 7. Deductions -3,000.00 207,669.66 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 31,541,644.76 1,100,744.28 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,100,744.28