Dept. of Trans. PROGRESS Serial No. Contract No. 17-268-16-56 04-0A7104 PROGRESS PAYMENT VOUCHER %complete: %time: 63% 58% Location: Federal Project: 04-ALA-880-28.4/29.2 NHPA-8801(70) Progress payment No. 039 Payment period ending: 09-20-17 RGW CONSTRUCTION INC 550 GREENVILLE RD LIVERMORE CA 94550 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 26,973,850.11 1,294,260.78 2. a. Extra Work 4,288,949.36 203,166.62 b. Adustment Comp. 332,829.02 0.00 3. Materials on Hand 681,889.75 31,489.47 4. Earned Subject to Retention 32,277,518.24 1,528,916.87 5. Mobilization 5,080,000.00 0.00 6. Total Work Completed 36,675,628.49 7. Deductions -12,575.00 20,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 37,344,943.24 1,548,916.87 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,548,916.87